Project Troisdorf, Germany

Potable water distribution

Project details

Description

The Y-piece with the HP-flanges welded on and the d 315mm tee with hydrant connector (DN80) were individually constructed, produced and delivered within 2 weeks of the excavation.

Advantages:

  • individual adaptation of the products
  • quick delivery
  • space saving assemblies

Requirements

A transition from PE to PVC, to be realised as quickly as possible.

Specifications

Size d
315 mm
Size DN/OD
300 mm
Werkstoff
PE 100
SDR
17

Used products

More case studies