Upper Silesia Gas Works, Poland

Relining of an old steel pipe (gas)

Project details

Description

Due to the extremely high demands in the pressure test re-enforced transition connections were supplied by us for the welding of steel fittings into the PE 100 pipe system.

Requirements

Compliance with the DVGW VP 600 Test Criteria for the construction 1h test with 40 bar, 20 ° C.

Specifications

Size d
500 mm
Size DN/OD
500 mm
Werkstoff
PE 100
SDR
11 & 7,4